Name: trueppm-scheduler
Version: 0.4.0b1
Summary: Critical-path method (CPM) and Monte Carlo schedule-risk engine for project management
Project-URL: Homepage, https://trueppm.com
Project-URL: Documentation, https://docs.trueppm.com/features/scheduler
Project-URL: Repository, https://gitlab.com/trueppm/trueppm
Project-URL: Issues, https://gitlab.com/trueppm/trueppm/-/issues
Project-URL: Changelog, https://gitlab.com/trueppm/trueppm/-/blob/main/packages/scheduler/CHANGELOG.md
Author: Kelly Hair
License-Expression: Apache-2.0
License-File: LICENSE
Keywords: cpm,critical-path,gantt,monte-carlo,networkx,pert,project-management,project-scheduling,risk-analysis,schedule-risk,scheduling
Classifier: Development Status :: 4 - Beta
Classifier: Intended Audience :: Developers
Classifier: Intended Audience :: Information Technology
Classifier: License :: OSI Approved :: Apache Software License
Classifier: Operating System :: OS Independent
Classifier: Programming Language :: Python :: 3
Classifier: Programming Language :: Python :: 3.11
Classifier: Programming Language :: Python :: 3.12
Classifier: Programming Language :: Python :: 3.13
Classifier: Topic :: Office/Business :: Scheduling
Classifier: Topic :: Scientific/Engineering :: Information Analysis
Classifier: Topic :: Scientific/Engineering :: Mathematics
Classifier: Topic :: Software Development :: Libraries
Classifier: Topic :: Software Development :: Libraries :: Python Modules
Classifier: Typing :: Typed
Requires-Python: >=3.11
Requires-Dist: networkx<4,>=3.0
Requires-Dist: numpy<3,>=1.26
Provides-Extra: dev
Requires-Dist: diff-cover<10.0,>=9.0; extra == 'dev'
Requires-Dist: hypothesis<7.0,>=6.0; extra == 'dev'
Requires-Dist: mutmut==3.8.0; extra == 'dev'
Requires-Dist: mypy<2.0,>=1.0; extra == 'dev'
Requires-Dist: pytest-cov<8.0,>=4.0; extra == 'dev'
Requires-Dist: pytest<10.0,>=7.0; extra == 'dev'
Requires-Dist: ruff<1.0,>=0.8; extra == 'dev'
Requires-Dist: types-networkx<4,>=3.0; extra == 'dev'
Description-Content-Type: text/markdown

# trueppm-scheduler

[![PyPI version](https://img.shields.io/pypi/v/trueppm-scheduler.svg)](https://pypi.org/project/trueppm-scheduler/)
[![PyPI downloads](https://img.shields.io/pypi/dm/trueppm-scheduler.svg)](https://pypi.org/project/trueppm-scheduler/)
[![CI](https://gitlab.com/trueppm/trueppm/badges/main/pipeline.svg)](https://gitlab.com/trueppm/trueppm/-/pipelines)
[![License](https://img.shields.io/badge/license-Apache%202.0-blue.svg)](https://www.apache.org/licenses/LICENSE-2.0)

**Project-schedule math as a library — critical path and delivery-risk forecasting, without a 500 MB desktop app or a SaaS subscription.**

Answer the two questions every plan has to answer:

- **"What's the earliest this can finish, and which tasks can't slip?"** — a full forward/backward critical-path pass computes early/late dates, total and free float, and flags the tasks on the critical path.
- **"How confident are we in that date?"** — Monte Carlo simulation turns three-point estimates into a P50/P80/P95 forecast, so you can commit to a date you'll actually hit instead of the best-case one.

It's pure Python with just `networkx` and `numpy` underneath — no Django, no web server, no GUI. Drop it into a backend, a data pipeline, a Jupyter notebook, or a CLI and get the same engine that powers the [TruePPM](https://trueppm.com) platform.

### Why reach for this

- **Real scheduling semantics, not a toy.** All four dependency types (finish-to-start, start-to-start, finish-to-finish, start-to-finish) with lead/lag on every link — most lightweight schedulers only do finish-to-start, which cannot express an overlap or a wait without faking it with a dummy task.
- **Working-time aware.** A built-in working-day calendar skips weekends and honors holiday exceptions, so durations resolve to real delivery dates.
- **Risk forecasting built in.** PERT-Beta Monte Carlo, numpy-vectorized at ~10k runs/sec — the difference between "due March 3" and "70% likely by March 3, 95% by March 14."
- **Fails loud on bad input.** Cycle detection that names the offending task IDs, plus up-front validation of durations, lag, and project span — no silent wrong answers, no spinning on a degenerate graph.
- **Embeds anywhere.** Two dependencies, no framework. Serialize a plan to JSON, schedule it, and read back structured results.

## Features

- Forward/backward CPM pass with all four dependency types (FS, SS, FF, SF), total/free float, and critical-path flagging
- Calendar-aware working-day arithmetic (weekend skip + holiday exceptions), with optional per-task calendars for mixed-team schedules
- Monte Carlo schedule-risk simulation via PERT-Beta distributions (numpy-vectorized, ~10k runs/sec) → P50/P80/P95 completion dates
- Hybrid agile/waterfall forecasting — mark a task `delivery_mode=SCRUM` with a `story_points` estimate and Monte Carlo samples its duration from the team's own velocity history instead of a per-task PERT guess, so a project can mix sprint-delivered and traditionally-estimated work in one simulation
- Explainable results — `derive_value()` answers "why is this date what it is?" for any early/late/float value, naming the exact predecessor, dependency type, and lag that won, plus every constraint it beat
- JSON round-tripping for plans (`Project.from_json()` / `Project.to_json()`)
- CLI: `trueppm-scheduler schedule` / `trueppm-scheduler monte-carlo`

## Install

```bash
pip install trueppm-scheduler
```

Requires Python 3.11+.

## Quick start

```python
from datetime import date, timedelta
from trueppm_scheduler import schedule, Calendar, Project, Task, Dependency, DependencyType

calendar = Calendar()  # Mon–Fri, no holidays (whole-day scheduling)
task_a = Task(id="t-1", name="Design", duration=timedelta(days=5))
task_b = Task(id="t-2", name="Build",  duration=timedelta(days=10))
dep = Dependency(predecessor_id="t-1", successor_id="t-2", dep_type=DependencyType.FS)

project = Project(
    id="p-1",
    name="My Project",
    start_date=date(2026, 1, 5),
    tasks=[task_a, task_b],
    dependencies=[dep],
    calendar=calendar,
)

result = schedule(project)
build = next(t for t in result.tasks if t.id == "t-2")
print(build.early_finish)  # 2026-01-23 (15 working days from 2026-01-05, across two weekends)
```

> **Scheduling granularity.** The engine schedules in whole working-day units.
> `Calendar.hours_per_day` and `Calendar.timezone` round-trip through
> serialization for API parity but are **not** consumed by the CPM or Monte Carlo
> passes — they do not change any computed date. Sub-day scheduling is a future
> change.

### Duration and lag are counted in different units

This trips people up, so it is worth stating plainly:

| Input | Unit |
|-------|------|
| `Task.duration` (and every PERT estimate) | **Working days** — weekends and calendar exceptions are skipped |
| `Dependency.lag` | **Calendar days** — the offset is applied as elapsed time, and only the resulting date is then snapped forward to the next working day |

So a 5-working-day task starting Monday finishes Friday, not the following
Tuesday. But a 2-day FS lag after a Friday finish does **not** buy two working
days of wait — the weekend absorbs it:

```python
# Predecessor finishes Friday 2026-01-09, Mon–Fri calendar, FS link.
#
#   lag=0d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=1d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=2d  → successor starts Mon 2026-01-12   (1 working day later)
#   lag=3d  → successor starts Tue 2026-01-13   (2 working days later)
#   lag=4d  → successor starts Wed 2026-01-14   (3 working days later)
```

If you need a wait of *n* working days, size the lag against the calendar the
successor will actually land on — or model the wait as a zero-resource task,
which is duration-counted and therefore calendar-aware end to end.

Negative lag (lead) is supported and follows the same calendar-day rule, snapping
backward to the previous working day.

### Per-task calendars

By default every task is scheduled on the single `Project.calendar`. A task can
instead opt into its own working week — useful when one schedule spans teams or
projects that keep different calendars:

```python
seven_day = Calendar(working_days=0b111_1111)  # every day is a working day
support = Task(id="t-3", name="Hotfix", duration=timedelta(days=3), calendar_id="ops")

project = Project(
    id="p-1",
    name="My Project",
    start_date=date(2026, 1, 5),
    tasks=[task_a, support],
    calendar=Calendar(),                 # pass-level default (Mon–Fri)
    calendars={"ops": seven_day},        # registry tasks opt into by id
)
```

Conventions:

- **Duration** arithmetic uses the task's *own* calendar (`calendar_id` → entry in
  `Project.calendars`). A `calendar_id` of `None`, or one with no matching entry,
  falls back to the pass-level `Project.calendar` — never an error.
- **Lag** on a dependency edge is applied as calendar days (above) and then
  snapped on the **successor's** calendar: the constraint lands where the wait is
  actually consumed.
- It is fully backward compatible — a project with no `calendars` registry
  schedules byte-for-byte as before.
- Both passes honor them: the CPM `schedule()` pass (early/late dates, float,
  criticality) and `monte_carlo()`. A fully deterministic mixed-calendar project
  simulates to precisely its CPM finish date, so the two agree by construction.

See [the full documentation](https://docs.trueppm.com/features/scheduler) for CPM output fields, Monte Carlo usage, and CLI reference.

## Explaining a result

The CPM pass picks the `max` (forward) or `min` (backward) of several candidate
constraints for each date, then moves on — it doesn't remember which one won.
`derive_value()` replays that decision for a single task and value, and names
the constraint that actually set it:

```python
from trueppm_scheduler import derive_value, Quantity

d = derive_value(project, task_id="t-2", quantity=Quantity.EARLY_START)
print(d.value, d.binding.kind, d.binding.source_task_name, d.binding.dep_type)
# 2026-01-12 predecessor_fs Design FS — Build starts when Design finishes on an FS link

for c in d.contributions:
    print(c.kind, c.source_task_name, c.is_binding)  # every constraint considered, winner flagged
```

This is what lets a UI (or an AI agent) answer "why is this task starting on the
17th?" with the actual dependency instead of a guess — the value returned is
computed the same way the engine computed it, not re-derived heuristically.

## Mixing agile and waterfall in one schedule

Real programs are rarely pure CPM or pure Scrum. A task can opt into
sprint-based uncertainty instead of a three-point estimate:

```python
from trueppm_scheduler import DeliveryMode, Task

sprint_work = Task(
    id="t-4",
    name="Checkout redesign",
    duration=timedelta(days=10),      # fallback if delivery_mode is later cleared
    delivery_mode=DeliveryMode.SCRUM,
    story_points=21,
)

project = Project(
    ...,
    tasks=[task_a, task_b, sprint_work],
    velocity_samples=[18, 22, 15, 24, 19],  # the team's last five sprints
)
```

`monte_carlo()` then samples `sprint_work`'s duration from how many sprints the
team's own velocity history says 21 points takes — not from a PERT guess nobody
on the team would stand behind — while every other task in the same run still
uses its three-point estimate. `DeliveryMode.WATERFALL` (the default) is
unaffected; mixing modes is opt-in per task.

## Interpreting the output

The two entry points answer different questions, and their outputs are not the
same kind of thing. Reading a `schedule()` date as if it were a commitment is
the single most common way to misuse this library.

**`schedule()` returns one date, and it is the optimistic one.** The CPM finish
is the *earliest feasible* completion — the date you get if every task takes
exactly the duration you estimated, no task slips, and no risk fires. It is a
point on a distribution, not the distribution. Nothing about the forward pass
makes that point likely; it is simply the arithmetic consequence of the numbers
you fed it.

**`monte_carlo()` returns the distribution that date sits in.** Sampling each
task's duration and re-running the network thousands of times produces the
range of finishes the plan can actually deliver:

| Percentile | Reading | Use it for |
|------------|---------|------------|
| `p50` | Half the simulated runs finished on or before this date. In practice it lands close to the CPM finish. | A midpoint, never a commitment |
| `p80` | 4 in 5 runs finished by this date. | **The commitment date** — internal and stakeholder plans |
| `p95` | 19 in 20 runs finished by this date. | Contractual deadlines, launch dates, regulatory submissions |

So a CPM finish of `2026-03-03` and a P80 of `2026-03-14` do not disagree. They
say: *the plan can finish on March 3, and it will finish by March 14 four times
out of five.* Committing to March 3 is committing to a coin flip.

Two consequences worth internalizing:

- **A task with no three-point estimate contributes no uncertainty.** It uses
  its fixed `duration` on every run, so a project where nothing is estimated
  simulates to precisely the CPM finish — `p50 == p80 == p95`. That is a correct
  result, not a broken one: you asked what varies, and the answer was nothing.
  Add optimistic/most-likely/pessimistic values to the tasks that drive the date
  (`MonteCarloResult.sensitivity` ranks them) to get a real band.
- **Widening the band is not pessimism.** A pessimistic estimate set to
  `most_likely × 1.2` produces a distribution too narrow to be useful — PERT
  derives σ as `(P − O) / 6`, so a P barely above M encodes near-certainty. The
  P value should describe a realistic bad day.

The same framing, with the underlying math, is in
[the Monte Carlo documentation](https://docs.trueppm.com/features/monte-carlo/#interpreting-results).

> **Scope.** Only this package's Python engine runs Monte Carlo. The companion
> Rust/WASM engine (`trueppm-wasm-scheduler`, used for browser-side and offline
> recompute) implements the deterministic CPM pass only — there is no
> probabilistic path there to keep in conformance.

## Errors and input limits

Every exception the engine raises subclasses `ValueError`, so one
`except ValueError` catches them all — but each is individually catchable:

| Exception | Raised when |
|-----------|-------------|
| `CyclicDependencyError` | The dependency graph contains a cycle. `.cycle` lists the task IDs forming it. |
| `SimulationCapExceeded` | `monte_carlo(runs=…)` exceeds `max_runs`, or the project has more tasks than `max_tasks`. |
| `InvalidScheduleInput` | The input is structurally valid but out of range (see limits below). |
| `UnknownTaskError` | `derive_value(project, task_id, …)` is called with a `task_id` that names no task in the project. |

The engine walks the working calendar one day at a time, so it validates input
up front rather than spinning on a degenerate project:

- **Calendar** — `working_days` must set at least one weekday bit (Mon–Sun); a
  calendar whose `exceptions` blanket the entire search window is rejected too.
- **Duration** — each task duration must be between `0` and `MAX_DURATION_DAYS`
  (`36_525`, ~100 years). Negative durations are rejected.
- **Lag** — each dependency lag must be within `±MAX_LAG_DAYS` (`36_525`).
- **Project span** — the cumulative span (every task's worst-case duration plus
  the magnitude of every lag) must stay under `MAX_PROJECT_SPAN_DAYS`
  (`366_000`, ~1000 years), regardless of task count.
- **Monte Carlo** — `runs` must be `>= 1`.

`Project.from_json()` also rejects the non-standard JSON literals `NaN`,
`Infinity`, and `-Infinity`.

```python
from trueppm_scheduler import schedule, InvalidScheduleInput

try:
    result = schedule(project)
except InvalidScheduleInput as e:
    print("Bad input:", e)  # "Task 't-1' duration exceeds the maximum of 36525 days (got …)."
```

## API stability and versioning

**The public API is the `__all__` surface of the top-level `trueppm_scheduler`
package** — the names you can import directly from `trueppm_scheduler`
(`schedule`, `monte_carlo`, `Project`, `Task`, `Dependency`, `DependencyType`,
`Calendar`, `ScheduleResult`, `MonteCarloResult`, the exception types, etc.).
Everything else — the `trueppm_scheduler.engine` internals, any underscore-
prefixed helper, and module layout — is **unstable** and may move or change
without notice.

This package is **`Development Status :: 4 - Beta`** as of 0.4.0b1: the public
API may still change before 1.0. **Pin an exact version** rather than a range:

```
trueppm-scheduler==0.4.0b1
```

Beta releases are pre-releases — `pip install trueppm-scheduler` skips them
unless you pass `--pre`. Breaking changes are recorded in
[`CHANGELOG.md`](https://gitlab.com/trueppm/trueppm/-/blob/main/packages/scheduler/CHANGELOG.md),
which also ships inside the wheel.

### Reproducibility (seeded runs)

Monte Carlo simulation is **reproducible for a fixed seed**: the same `seed`
always yields the same P50/P80/P95 forecast for the same input. This is a
supported, tested property you can rely on for reproducible reports and
regression baselines — not an implementation detail.

This is a statement about *repeatability of the sampling*, not about the shape
of the answer — a seeded Monte Carlo run still returns a probability
distribution. Do not confuse it with the deterministic single-date output of
`schedule()`, which is [a different thing entirely](#interpreting-the-output).

## Security

Found a vulnerability in the scheduling engine? Please report it privately —
do **not** open a public issue. Email **security@trueppm.com** or open a
confidential GitLab issue. Full policy, response SLAs, and safe-harbor terms are
in [`SECURITY.md`](https://gitlab.com/trueppm/trueppm/-/blob/main/SECURITY.md)
at the monorepo root.

## License

Apache 2.0